Route 160, Allardville to Route 8
Federal contribution
$473,500
Federal share50%
of $947.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 30, 2010
ApprovedJul 28, 2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- Jul 26, 2010(actual)
- Construction end
- Oct 14, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 15, 2010
- Construction end2 weeks earlyforecast Oct 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39752 in the federal list. How to read these figures.