Rehabilitating and Repaving Route 113
Federal contribution
$271,060
Federal share50%
of $545.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 30, 2010
ApprovedJul 28, 2010
Built
Approved 6 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- May 31, 2010(actual)
- Construction end
- Jul 7, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jun 15, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39754 in the federal list. How to read these figures.