Upgrading and Repaving Sections of Route 331, George’s Point (Route 330) Towards Boyd’s Cove (Route 340)

Georges Point, Newfoundland and Labrador

completeHighways and RoadsISF
Federal contribution
$1.4M
$1,371,422
Federal share33%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 29, 2010
Built
Program
Infrastructure Stimulus Fund
Construction start
May 31, 2010(actual)
Construction end
Sep 20, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Apr 21, 2010
  • Construction end6 weeks earlyforecast Oct 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39756 in the federal list. How to read these figures.