Upgrading and Repaving a Section of Route 210, Burin Peninsula Highway
Goobies, Newfoundland and Labrador
Federal contribution
$1.3M
$1,347,400
Federal share34%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 29, 2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Apr 26, 2010(actual)
- Construction end
- Aug 27, 2010(actual)
Against the original forecast
- Construction end2 months earlyforecast Oct 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39760 in the federal list. How to read these figures.