Highway 88 - Roadwork

Loon River First Nation, Alberta

completeHighways and RoadsISF
Federal contribution
$5.2M
$5,150,000
Federal share50%

of $10.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJan 28, 2010
ApprovedJul 23, 2010
2011
Built

Approved 6 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jan 12, 2011(actual)
Construction end
Oct 28, 2011(actual)

Against the original forecast

  • Construction start2 months earlyforecast Mar 15, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39771 in the federal list. How to read these figures.