Repairs of three access roads

Sainte-Anne-des-Plaines, Quebec

completeHighways and RoadsCC Top Up
Federal contribution
$1.7M
$1,669,772
Federal share27%

of $6.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 29, 2010
2011
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
Aug 2, 2010(actual)
Construction end
Aug 30, 2011(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Sep 21, 2010

Also in Sainte-Anne-des-Plaines

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39791 in the federal list. How to read these figures.