Improvement of Nicolas-Rioux Road

Saint-Eugène-de-Ladrière, Quebec

completeHighways and RoadsCC Top Up
Federal contribution
$127,486
Federal share33%

of $382.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 29, 2010
2011
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
Aug 9, 2010(actual)
Construction end
Jan 1, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2010
  • Construction end6 months lateforecast Jul 8, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39811 in the federal list. How to read these figures.