Improvement of Nicolas-Rioux Road
Saint-Eugène-de-Ladrière, Quebec
Federal contribution
$127,486
Federal share33%
of $382.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 29, 2010
2011
Built
Approved 8 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Parish of Saint-Eugène-De-Ladrière
- Construction start
- Aug 9, 2010(actual)
- Construction end
- Jan 1, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2010
- Construction end6 months lateforecast Jul 8, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39811 in the federal list. How to read these figures.