Back to projects

Four seasons skating rink

Grande-Vallée, Quebec

completeSportCC Top Up
Federal contribution
$40,140
Federal share32%

of $125.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 31, 2010
2011
Built

Approved 4 months before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Construction start
Nov 1, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2010
  • Construction end5 months lateforecast Oct 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39853 in the federal list. How to read these figures.