Four seasons skating rink
Federal contribution
$40,140
Federal share32%
of $125.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 31, 2010
2011
Built
Approved 4 months before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of Grande-Vallée
- Construction start
- Nov 1, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 1, 2010
- Construction end5 months lateforecast Oct 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39853 in the federal list. How to read these figures.