Reconstruction of Side Road 19
Federal contribution
$1.8M
$1,800,000
Federal share50%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 12, 2010
2011
Built
Approved 2 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Centre Wellington
- Construction start
- Jun 17, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2010
- Construction end4 weeks lateforecast Sep 30, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39868 in the federal list. How to read these figures.