Construction a cultural building

Cabano, Quebec

completeCultureCC Top Up
Federal contribution
$385,379
Federal share28%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 29, 2010
2011
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Cabano
Construction start
Oct 1, 2010(actual)
Construction end
Jul 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 1, 2010