Gore Bay Manitoulin Airport Runway Rehabilitation
Federal contribution
$1.7M
$1,676,100
Federal share50%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 3, 2010
ApprovedSep 21, 2010
2011
Built
Approved 7 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Burpee and Mills
- Construction start
- Sep 23, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 7, 2010
- Construction end2 months lateforecast Sep 1, 2011
Also in Gordon/Barrie Island
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39890 in the federal list. How to read these figures.