Stone Ridge Bridge Replacement
Federal contribution
$143,774
Federal share40%
of $360.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 29, 2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of New Brunswick
- Construction start
- Aug 18, 2010(actual)
- Construction end
- Nov 15, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 15, 2010
- Construction end7 weeks lateforecast Sep 30, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39891 in the federal list. How to read these figures.