Highway 11 Resurfacing

Oro-Medonte, Ontario

completeHighways and RoadsISF
Federal contribution
$4.3M
$4,330,057
Federal share27%

of $16.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 7, 2010
Built

Approved 2 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Jul 7, 2010(actual)
Construction end
Nov 5, 2010(actual)

Also in Oro-Medonte