Construction of a permanent festival tent in Trois-Bérets Park
Federal contribution
$619,875
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2010
2011
Built
Approved 7 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Municipality of Saint-Jean-Port-Joli
- Construction start
- Oct 5, 2010(actual)
- Construction end
- Aug 30, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2010
Also in Saint-Jean-Port-Joli
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39918 in the federal list. How to read these figures.