Recreation centre renovation
Federal contribution
$481,345
Federal share19%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2010
2011
Built
Approved 7 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Centre Des Loisirs De Fatima, I. M., Inc.
- Construction start
- Oct 11, 2010(actual)
- Construction end
- Jul 31, 2011(actual)
Against the original forecast
- Construction start6 months lateforecast Apr 1, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39968 in the federal list. How to read these figures.