Highway 1 - Anderson River Bridge no. 552

Boston Bar, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.8M
$1,800,000
Federal share50%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2010
2011
Built

Approved 5 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 1, 2010(actual)
Construction end
Dec 21, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 3, 2010

Also in Boston Bar

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40248 in the federal list. How to read these figures.