Rehabilitation of Highway 579
Federal contribution
$800,000
Federal share50%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 29, 2010
2011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Oct 18, 2010(actual)
- Construction end
- Jul 25, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 1, 2010
- Construction end3 months earlyforecast Oct 15, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40464 in the federal list. How to read these figures.