Rehabilitation of Highway 881
Federal contribution
$2.2M
$2,193,000
Federal share50%
of $4.4M total eligible cost; the rest comes from other partners.
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Aug 19, 2010(actual)
- Construction end
- Sep 15, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 3, 2010
- Construction end6 months earlyforecast Mar 31, 2011
Also in Lac La Biche County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40489 in the federal list. How to read these figures.