Construction of a Multipurpose Centre
Federal contribution
$538,100
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2010
2011
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Town of Maniwaki
- Construction start
- Oct 29, 2010(actual)
- Construction end
- Jun 23, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast Sep 20, 2010
- Construction end3 weeks earlyforecast Jul 15, 2011
Also in Maniwaki
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40540 in the federal list. How to read these figures.