Back to projects

Program for the renewal of drinking water and wastewater pipes

Mercier, Quebec

completeWastewaterISF
Federal contribution
$88,965
Federal share31%

of $287.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2011
20102011
Built

Approved 13 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Mercier
Construction start
Jun 9, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009
  • Construction end7 months lateforecast Mar 31, 2011