Program for the renewal of drinking water and wastewater pipes

Huntingdon, Quebec

completeWastewaterISF
Federal contribution
$105,954
Federal share31%

of $341.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 24, 2010
20102011
Built

Approved 3 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Huntingdon
Construction start
Jun 9, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009
  • Construction end7 months lateforecast Mar 31, 2011