Program for the renewal of drinking water and wastewater pipes
Deschambault-Grondines, Quebec
Federal contribution
$216,231
Federal share31%
of $697.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedFeb 8, 2010
ApprovedJun 30, 2010
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Deschambault-Grondines
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
- Construction end7 months lateforecast Mar 31, 2011
Also in Deschambault-Grondines
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40596 in the federal list. How to read these figures.