Program for the renewal of drinking water and wastewater pipes

Deschambault-Grondines, Quebec

completeWastewaterISF
Federal contribution
$216,231
Federal share31%

of $697.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedFeb 8, 2010
ApprovedJun 30, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 9, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009
  • Construction end7 months lateforecast Mar 31, 2011