Repairs to Route 352 in Saint-Stanislas

Saint-Stanislas (Mauricie), Quebec

completeHighways and RoadsISF
Federal contribution
$309,867
Federal share36%

of $870.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2011
2011
Built

Approved 12 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Sep 20, 2010(actual)
Construction end
Sep 28, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 1, 2010
  • Construction end2 weeks earlyforecast Oct 15, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40764 in the federal list. How to read these figures.