Program for the renewal of drinking water and wastewater pipes
Saint-Antoine-de-Tilly, Quebec
Federal contribution
$376,917
Federal share31%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 9, 2010
20102011
Built
Approved 2 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Saint-Antoine-de-Tilly
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
- Construction end7 months lateforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 40950 in the federal list. How to read these figures.