Sanitary Sewer System - Extraneous Flow Reduction and Asset Rehabilitation
Federal contribution
$833,333
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
2011
Built
Approved 9 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Kingston
- Construction start
- Sep 13, 2010(actual)
- Construction end
- Aug 19, 2011(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Nov 1, 2010
Also in Kingston
- City of Kingston Third Crossing Bridge$60.0M
- Ministry of Transportation Ontario Eastern Region New Ferry Vessels$31.3M
- Kingston Wastewater Treatment Plant Upgrades$25.0M
- Isabel Bader Centre for the Performing Arts at Queen's University at Kingston$15.0M
- Long Range Battery Electric Conventional Transit Buses and Bio- Diesel/Hybrid Buses$12.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41046 in the federal list. How to read these figures.