Back to projects

Interior Reservoir Coatings - Hanlan South Reservoir Cell

Mississauga, Ontario

completeDrinking WaterISF
Federal contribution
$668,968
Federal share30%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2011
2011
Built

Approved 9 months before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 27, 2010(actual)
Construction end
Mar 31, 2011(actual)

Also in Mississauga