Highway 1 Resurfacing - Horseshoe Bay Underpass Deck
West Vancouver, British Columbia
Federal contribution
$101,356
Federal share11%
of $900.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 19, 2010
2011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Nov 8, 2010(actual)
- Construction end
- Aug 22, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 1, 2010
- Construction end3 months lateforecast Jun 2, 2011
Also in West Vancouver