Highway 97 Resurfacing - Summerland/Osoyoos

Osoyoos, British Columbia

completeHighways and RoadsISF
Federal contribution
$746,174
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 19, 2010
ApprovedSep 8, 2010
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 12, 2010(actual)
Construction end
Dec 9, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Aug 1, 2010
  • Construction end3 weeks earlyforecast Dec 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41240 in the federal list. How to read these figures.