Back to projects

Highway 99 Resurfacing

Delta, British Columbia

completeHighways and RoadsISF
Federal contribution
$644,629
Federal share24%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 19, 2010
ApprovedSep 8, 2010
2011
Built

Approved 3 weeks after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 28, 2010(actual)
Construction end
Jul 31, 2011(actual)

Against the original forecast

  • Construction start3 months lateforecast Aug 1, 2010
  • Construction end2 months lateforecast May 31, 2011

Also in Delta

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41243 in the federal list. How to read these figures.