completeRecreationCC
Federal contribution
$1.4M
$1,375,237
Federal share26%

of $5.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 20, 2010
20112012
Built
Program
Building Canada Fund - Communities Component
Construction start
Dec 13, 2010(actual)
Construction end
Jan 28, 2012(actual)

Against the original forecast

  • Construction start3 months earlyforecast Mar 1, 2011
  • Construction end8 weeks lateforecast Nov 30, 2011

Also in Abrams Village