Program for the renewal of drinking water and wastewater pipes
Sainte-Victoire-de-Sorel, Quebec
Federal contribution
$554,987
Federal share31%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
20102011
Built
Approved 9 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Sainte-Victoire-de-Sorel
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
- Construction end7 months lateforecast Mar 31, 2011