Back to projects

Program for the renewal of drinking water and wastewater pipes

R.I.A. du Bas-Richelieu, Quebec

completeWastewaterISF
Federal contribution
$131,449
Federal share31%

of $424.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 8, 2011
20102011
Built

Approved 9 months before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jun 9, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 6, 2009
  • Construction end7 months lateforecast Mar 31, 2011

Also in R.I.A. du Bas-Richelieu

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41302 in the federal list. How to read these figures.