Program for the renewal of drinking water and wastewater pipes
Federal contribution
$145,951
Federal share31%
of $471.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 30, 2010
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Saint-Fulgence
- Construction start
- Jun 9, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 6, 2009
- Construction end7 months lateforecast Mar 31, 2011
Also in Saint-Fulgence