Replacement of Refrigeration Equipment

Danville, Quebec

completeSportCC
Federal contribution
$38,651
Federal share24%

of $160.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20122013201420152016
Built

Approved 4 years before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Feb 28, 2012(actual)
Construction end
Jan 26, 2013(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Mar 15, 2012
  • Construction end14 months earlyforecast Mar 31, 2014

Also in Danville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41339 in the federal list. How to read these figures.