Ada Johnson Park Washroom Building
Federal contribution
$53,932
Federal share22%
of $250.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
2011
Built
Approved 7 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Aurora
- Construction start
- Dec 15, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Also in Aurora
- HVAC Upgrades; Bottle fill station; Gym Divider Wall$7.6M
- HVAC upgrades in schools and portables; Windows replacement, Portable replacements$6.3M
- HVAC System in portable classrooms$4.2M
- Cooling Centres; Window Replacement$4.1M
- HVAC Upgrades (schools); Wifi Access Points and network switches; Security Access (communication/paging system)$3.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41406 in the federal list. How to read these figures.