Resurfacing of Highway 5

Heffley Creek, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.4M
$1,449,210
Federal share50%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 18, 2011
2011
Built

Approved 5 months before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 20, 2010(actual)
Construction end
Oct 25, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Aug 30, 2010