Halifax Harbourwalk Seawall Repair and Recapitalization Program
Federal contribution
$56,448
Federal share38%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
2011
Built
Approved 9 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Jan 4, 2011(actual)
- Construction end
- Mar 18, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Oct 31, 2010
- Construction end3 weeks lateforecast Feb 28, 2011
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41666 in the federal list. How to read these figures.