Saturna and Mayne Island Roads Resurfacing
South Gulf Islands, British Columbia
Federal contribution
$405,000
Federal share50%
of $810.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 18, 2011
2011
Built
Approved 5 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Sep 30, 2010(actual)
- Construction end
- Oct 6, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 6, 2010
- Construction end3 weeks earlyforecast Oct 29, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41668 in the federal list. How to read these figures.