Facade Rehabilitation - Art Gallery of Nova Scotia

Halifax, Nova Scotia

completeCultureISF
Federal contribution
$138,228
Federal share14%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2011
2011
Built

Approved 3 months before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Jan 15, 2011(actual)
Construction end
Oct 30, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Dec 10, 2010
  • Construction end4 weeks lateforecast Sep 30, 2011