Facade Rehabilitation - Art Gallery of Nova Scotia
Federal contribution
$138,228
Federal share14%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2011
2011
Built
Approved 3 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Jan 15, 2011(actual)
- Construction end
- Oct 30, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Dec 10, 2010
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41671 in the federal list. How to read these figures.