Repairs to Carriage House at Government House
Federal contribution
$117,935
Federal share39%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2011
2011
Built
Approved 3 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Feb 7, 2011(actual)
- Construction end
- Jul 12, 2011(actual)
Against the original forecast
- Construction end4 weeks lateforecast Jun 15, 2011
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41672 in the federal list. How to read these figures.