Back to projects

Reeves Street Repairs (Phase 1) - Sydney

Cape Breton, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$21,120
Federal share23%

of $90.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2011
2011
Built

Approved 3 months before the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Nov 15, 2010(actual)
Construction end
Dec 16, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Oct 11, 2010
  • Construction end3 months earlyforecast Mar 31, 2011

Also in Cape Breton