Burgoyne Bridge Replacement

Niagara, Ontario

completeHighways and RoadsMIC
Federal contribution
$18.2M
$18,167,000
Federal share33%

of $54.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 10, 2010
ApprovedMar 16, 2012
2011201320152017
Built

Approved 15 months after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Ultimate recipient
City of Niagara Falls
Construction start
Mar 3, 2014(actual)
Construction end
Oct 17, 2017(actual)

Against the original forecast

  • Construction start8 months lateforecast Jul 15, 2013
  • Construction end3 months earlyforecast Jan 31, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41701 in the federal list. How to read these figures.