Back to projects

Renovation of Sherbrooke, Deauville and Brompton water treatment plants

Sherbrooke, Quebec

completeWastewaterLUCC
Federal contribution
$6.5M
$6,482,568
Federal share33%

of $19.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 16, 2011
201220132014201520162017
Built

Approved 6 months before the announcement.

Program
Building Canada Fund - Large Urban Centres Component
Ultimate recipient
City of Sherbrooke
Construction start
Apr 1, 2011(actual)
Construction end
Dec 31, 2016(actual)

Against the original forecast

  • Construction end21 months lateforecast Mar 31, 2015

Also in Sherbrooke

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41958 in the federal list. How to read these figures.