Back to projects

Phase 3 of the Joseph and Wolf Lebovic Jewish Community Campus

Vaughan, Ontario

completeRecreationMIC
Federal contribution
$4.8M
$4,828,702
Federal share50%

of $9.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2013
20122013
Built

Approved 23 months before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Mar 1, 2012(actual)
Construction end
Jul 26, 2013(actual)

Against the original forecast

  • Construction end2.6 years earlyforecast Mar 1, 2016

Also in Vaughan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 42003 in the federal list. How to read these figures.