Brampton Zum Project (AcceleRide) - Phase II

Brampton, Ontario

completePublic TransitCSIF
Federal contribution
$38.1M
$38,078,301
Federal share30%

of $126.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 6, 2007
ApprovedJan 20, 2012
2007201020132016
Built

Approved 4.9 years after the announcement.

Program
Canada Strategic Infrastructure Fund
Construction start
Oct 1, 2013(actual)
Construction end
Jul 15, 2018(actual)

Against the original forecast

  • Construction end3 months lateforecast Mar 31, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 42639 in the federal list. How to read these figures.