Brampton Zum Project (AcceleRide) - Phase II
Federal contribution
$38.1M
$38,078,301
Federal share30%
of $126.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 6, 2007
ApprovedJan 20, 2012
2007201020132016
Built
Approved 4.9 years after the announcement.
- Program
- Canada Strategic Infrastructure Fund
- Ultimate recipient
- Corporation of the City of Brampton
- Construction start
- Oct 1, 2013(actual)
- Construction end
- Jul 15, 2018(actual)
Against the original forecast
- Construction end3 months lateforecast Mar 31, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 42639 in the federal list. How to read these figures.