Plessis Road Underpass
Federal contribution
$25.0M
$25,000,000
Federal share33%
of $75.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 19, 2012
20132014201520162017
Built
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Winnipeg
- Construction start
- Jul 29, 2013(actual)
- Construction end
- Mar 31, 2017(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2013
- Construction end8 weeks lateforecast Jan 31, 2017
Also in MacDonald
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 43130 in the federal list. How to read these figures.