Construction of Shipshaw Multi-Service Centre

Chicoutimi-Le Fjord, Quebec

completeCultureLUCC
Federal contribution
$1.2M
$1,191,494
Federal share33%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2013201420152016
Built

Approved 3.7 years before the announcement.

Program
Building Canada Fund - Large Urban Centres Component
Ultimate recipient
City of Saguenay
Construction start
Jan 1, 2013(actual)
Construction end
Jan 19, 2015(actual)

Against the original forecast

  • Construction start4 months lateforecast Sep 4, 2012
  • Construction end17 months lateforecast Aug 30, 2013

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 43513 in the federal list. How to read these figures.