Construction of Shipshaw Multi-Service Centre
Federal contribution
$1.2M
$1,191,494
Federal share33%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2013201420152016
Built
Approved 3.7 years before the announcement.
- Program
- Building Canada Fund - Large Urban Centres Component
- Ultimate recipient
- City of Saguenay
- Construction start
- Jan 1, 2013(actual)
- Construction end
- Jan 19, 2015(actual)
Against the original forecast
- Construction start4 months lateforecast Sep 4, 2012
- Construction end17 months lateforecast Aug 30, 2013