Henderson Highway Wastewater Collection System
Federal contribution
$2.0M
$2,000,000
Federal share33%
of $6.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2013201420152016
Built
Approved 3.2 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of St. Clements
- Construction start
- Nov 1, 2013(actual)
- Construction end
- Jan 12, 2016(actual)
Against the original forecast
- Construction end14 months lateforecast Nov 1, 2014
Also in East Selkirk
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 43806 in the federal list. How to read these figures.