Highway 400 Reconstruction - Simcoe County
Bradford West Gwillimbury, Ontario
Federal contribution
$39.7M
$39,672,500
Federal share48%
of $83.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 12, 2013
ApprovedAug 21, 2013
201420152016
Built
Approved 4 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Ontario
- Construction start
- May 1, 2014(actual)
- Construction end
- Sep 30, 2016(actual)
Against the original forecast
- Construction end2 months lateforecast Jul 31, 2016