Highway 17 Rehabilitation - Nipissing District

Bonfield, Ontario

completeHighways and RoadsMIC
Federal contribution
$5.0M
$5,049,965
Federal share50%

of $10.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 7, 2013
ApprovedNov 19, 2013
20142015
Built

Approved 5 months after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Ultimate recipient
Province of Ontario
Construction start
Apr 1, 2014(actual)
Construction end
Sep 1, 2015(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Feb 28, 2014
  • Construction end5 weeks lateforecast Jul 31, 2015

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44272 in the federal list. How to read these figures.