Highway 17 Rehabilitation - Nipissing District
Federal contribution
$5.0M
$5,049,965
Federal share50%
of $10.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 7, 2013
ApprovedNov 19, 2013
20142015
Built
Approved 5 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Province of Ontario
- Construction start
- Apr 1, 2014(actual)
- Construction end
- Sep 1, 2015(actual)
Against the original forecast
- Construction start5 weeks lateforecast Feb 28, 2014
- Construction end5 weeks lateforecast Jul 31, 2015
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44272 in the federal list. How to read these figures.